Package 2A – Construction and Completion of 1130 MLD Langat 2, Water Treatment Plant

Contract Value
RM 17,787,703
Client
Salcon MMCES AZSB JV Sdn Bhd
Location
Langat 2, Selangor
Scope
Supply, Delivery Of Material, Installation Including Tools And Machineries Testing And Commissioning Of Mechanical And Instrument (Installation Works)

The Langat 2 Water Treatment Plant is a major water infrastructure project with a treatment capacity of 1,130 MLD, making it one of the largest water treatment plants in Malaysia. The project scope comprises the installation of mechanical and process systems, instrumentation and control systems, as well as chemical dosing systems required for the complete water treatment process. The works support the plant’s overall operation, ensuring reliable and efficient treatment and supply of potable water to meet the region’s growing water demand.

  • Preliminaries works
  • Treatment Plant
  • Pumping Plant
  • Chemical Plant
  • Sludge Plant
  • Instrumentation, Clear Water Tank & Wash Water Recovery Plant
Contract Value

RM 17,787,703

Status
Completed
Completion date
21 August 2020
Client
Salcon MMCES AZSB JV Sdn Bhd
Location
Langat 2, Selangor