Proposed 120 MLD Conventional Water Treatment Plant Intakes, Services Tank, Installation Of Raw Water and Clean Water Pipe

Contract Value
RM 3,000,000
Client
Salcon Engineering Berhad
Location
Kuala Terengganu, Malaysia
Scope
Services Tank, Installation Of Mechanical Equipment

The Bukit Berapit Water Treatment Plant is a key water infrastructure project developed to provide a reliable treated water supply to Kuala Terengganu and the surrounding areas. The project scope includes the construction and installation of the raw water intake system, mechanical and process systems, instrumentation and control systems, chemical dosing systems, and associated equipment required for the complete operation of the water treatment plant.

  • Supply manpower for the installation of all mechanical and instrumentation which comprises of design engineering, services, labour, material for construction up to completion assisting in testing and commissioning
Contract Value

RM 3,000,000

Status
Completed
Completion date
30 May 2021
Client
Salcon Engineering Berhad
Location
Kuala Terengganu, Malaysia