Construction And Completion Of 1130 MLD Langat 2 WTP

Contract Value
RM 8,181,080
Client
Salcon MMCES AZSB JV Sdn Bhd
Location
Langat 2, Selangor
Scope
Fabrication, Delivery, Installation And Testing & Commissioning of Lamella System C/w Accessories

The Langat 2 Water Treatment Plant, with a treatment capacity of 1,130 MLD, includes the fabrication and installation of a lamella clarification system designed to enhance the water treatment process and achieve clarified water quality of up to 2 NTU. The scope covers the fabrication, installation, testing and commissioning of the lamella system and associated mechanical and process components to ensure efficient and reliable clarification performance.

  • Supply of labour to fabricate lamella plates
  • Fabricate channel & weir plates
  • Installation of 20 Lamella Tanks Including Lifting Equipment
  • Supply and install SS mounting anchor and 50mm SS angle for channel PE leveling for 20 units of tank
Contract Value

RM 8,181,080

Status
Completed
Completion date
30 June 2016
Client
Salcon MMCES AZSB JV Sdn Bhd
Location
Langat 2, Selangor